StratXG Digital PMO
Programme Governance Platform
Metro Rail Corridor — Phase 2  ·  38.6 km  ·  World Bank / JICA Funded  ·  Ahmedabad PMO Hub
LIVE
--:--:-- IST
PH
PMO Head

Programme Command Centre

Metro Rail Corridor — Phase 2  ·  38.6 km  ·  6 packages  ·  84 contracts active

₹4,280 Cr
Programme Value
57%
Physical Progress
0.91
SPI
9
Open Escalations
Contracts Active
84
6 packages
12 IPC pending certification
Schedule SPI
0.91
vs 1.0 target
▼ –0.03 vs last month
Cost CPI
1.03
On budget
▲ +3% cost efficiency
Open Escalations
9
3×L2 · 1×L3
4 SLA breached
Open Risks
23
7 High · 11 Medium
3 new this week
Compliance Score
82%
World Bank ESF
▲ +4% vs last quarter
Variation Orders
31
₹124 Cr cumulative
8 pending approval
DSR Compliance
91%
Submitted today
▲ 284/312 sites
Package progress — actual vs planned6 contract packages
SPI trend — 12 monthsTarget = 1.0
Health RAG — 84 contracts
Green (49) Amber (22) Red (13)
This week's milestones
Milestones due14
Achieved on time9
Delayed3
At risk (next 7 days)5
IPC certifications issued4
Variation orders raised3
New escalations this week2
EVM snapshot
Governance Structure
Three-tier programme governance · Stage-gate control · RACI matrix · Funder interface
Three-tier governance architecture
Tier 1 — Strategic: Programme Steering Committee
Client PIU + World Bank TTL + JICA Officer + StratXG PMO Head  ·  Monthly review  ·  Budget approval  ·  Funder compliance  ·  L3 escalation resolution
Tier 2 — Operational: PMO Management Committee
StratXG PMO Core Team + PMC Director + Package Managers  ·  Weekly review  ·  Schedule management  ·  Contract actions  ·  Issue resolution
Tier 3 — Execution: Site Teams
Contractor PMs + Resident Engineers + HSE Officers  ·  Daily reporting  ·  Progress tracking  ·  Quality control  ·  Safety compliance
Stage-gate status — all packagesG0–G5 milestone gates
PackageCurrent GateStatusNext Gate
Civil-1 (Depot)G4 — ConstructionOn trackG5 — Testing
Civil-2 (Viaduct)G4 — ConstructionAt riskG5 — Testing
Civil-3 (UG)G3 — Mech. Compl.DelayedG4 — Const.
Systems (E&M)G3 — Mech. Compl.On trackG4
Rolling StockG2 — Go-aheadCommissioningG3
Property Dev.G1 — Pre-const.At riskG2
Funder interface
World Bank (IBRD)
Infrastructure Project Loan
38% disbursedUSD 450M
JICA (ODA Loan)
Official Dev. Assistance
44% disbursedJPY 85B
Govt. of India
Central Grant
61% utilised₹1,200 Cr
State Govt.
Equity / VGF
52% utilised₹680 Cr
Contract Governance Suite
IPC certification · Variation orders · EoT assessment · LD tracking · FIDIC-aligned lifecycle management
Total Contracts
84
6 packages
IPC Pending
12
Certification due
3 overdue >10 days
Variation Orders
31
₹124 Cr cumulative
EoT Claims
7
2 agreed · 5 pending
LD Exposure
₹38 Cr
If delays persist
IPC Certification Pipeline — ActivePayment workflow tracker
IPC RefPackageContractorAmountSubmittedPMO StatusDays PendingAlert
IPC-CV1-14Civil-1 (Depot)L&T Civil₹42 Cr4 days agoCertified2—
IPC-CV2-09Civil-2 (Viaduct)Afcons₹68 Cr7 days agoUnder Review7Due today
IPC-CV3-06Civil-3 (UG)HCC-CRCHI JV₹31 Cr14 days agoDisputed14Overdue
IPC-SYS-07Systems E&MSiemens Mobility₹55 Cr3 days agoCertified1—
IPC-RS-04Rolling StockCRRC Qingdao₹210 Cr11 days agoPrior-review req.11Funder approval
IPC-PD-03Property Dev.Godrej Properties₹18 Cr5 days agoUnder Review5—
Contract risk indicators
Contracts with critical-path float <7d11
LD clauses triggered3
Performance bonds expiring <30 days4
Insurance renewals due <14 days2
Contractor financial risk watch1
Contracts at final account stage6
DLP monitoring active8
Variation orders — top 5 by value
Critical Path & EVM
Integrated Master Schedule · Float monitoring · Earned Value Management · Recovery planning
Programme SPI
0.91
Critical Activities
18
Zero float
Float <7 Days
31
Activities
Avg Delay
4.2 wks
Revised Completion
Mar '27
+4 months
Integrated Programme Schedule — Critical PathFloat threshold: 7 days  ·  ⚠ = zero float
EVM — Planned Value / Earned Value / Actual Cost12-month trend
Planned Value (PV) Earned Value (EV) Actual Cost (AC)
EVM performance indices
Schedule Performance Index (SPI)0.91
Cost Performance Index (CPI)1.03
Planned Value (PV) — to date₹2,960 Cr
Earned Value (EV) — to date₹2,630 Cr
Actual Cost (AC) — to date₹2,560 Cr
Schedule Variance (SV)–₹330 Cr
Cost Variance (CV)+₹70 Cr
Estimate at Completion (EAC)₹4,155 Cr
Variance at Completion (VAC)+₹125 Cr
Risk Register
ISO 31000 aligned · RAGB heatmap · Mitigation tracking · 23 open risks
Risk heatmap — Probability × Impact
Top risks — open & active23 total
Risk DescriptionProb.ImpactRating
UG tunnelling — ground settlementHighV.HighCritical
Rolling stock delivery delayHighHighHigh
Forest diversion clearance delayedHighHighHigh
HCC-CRCHI JV financial stressMediumV.HighHigh
Utility conflict — NH-48 sectionHighMediumMedium
Monsoon impact — Q2 civil progressHighMediumMedium
Land parcel dispute — Depot siteLowHighMedium
Risk treatment status by categoryISO 31000
Mitigated In treatment Open / new
Compliance Tracker
World Bank ESF · JICA Guidelines · MoEFCC · Labour standards · Procurement compliance
OVERDUE:  GRM Quarterly Report — 18 days late. World Bank TTL has flagged. Action required immediately by PMO Head.
DUE IN 5 DAYS:  ESCP Action 3.4 — Dust suppression audit at Civil-3 package sites.
Compliance matrix — regulatory, statutory & funder
Compliance by domain
World Bank disbursement conditions
Escalation & Alerts
4-level SLA matrix · Auto-escalation engine · Formal notice management · 9 open escalations
Open Escalations
9
SLA Breached
4
Immediate action
L2 Open
3
L3 Open
1
Resolved YTD
62
79% within SLA
Active escalation logSLA countdown live
RefPackageIssueLevelRaisedSLA RemainingOwnerStatus
ESC-088Civil-3 (UG)Tunnel face collapse — work haltedL33 days ago72h overdueSteering Cmt.Open
ESC-091Rolling StockCRRC delivery delay — 8 weeksL25 days ago3d overduePMC DirectorOpen
ESC-092Civil-2 (Via.)Forest diversion — HC stay orderL22 days ago12h overdueClient PIUOpen
ESC-093Civil-3 (UG)HCC-CRCHI — payment default riskL21 day ago14h leftPMC DirectorIn progress
ESC-089Systems E&MPower supply design change — ₹14 Cr impactL12 days ago4h leftPMO HeadIn progress
ESC-090Property Dev.Land parcel — court challenge filedL11 day ago8h leftPMO HeadIn progress
ESC-094Civil-1 (Depot)Piling NCR — quality holdL04h agoActivePMO OfficerIn progress
Escalation volume — 6 months
Automated notification queue
09:14 today — SMS + Email
L3 SLA breach — ESC-088 — Steering Committee notified
08:30 today — Email
IPC-RS-04 overdue — Funder prior-review pending 11 days
07:00 today — Dashboard
Float = 0 on Civil-3 Chainage 14–18 tunnelling activity
18:00 yesterday — Email
Performance bond CV3-06 expiring in 22 days
06:00 today — Dashboard
4-week look-ahead schedule due from all package PMs by Friday
Field Reports — Daily Site Returns (DSR)
GPS-tagged · Photo-verified · Mobile-first · Offline-capable · Drone integration
Live ground update feedUpdated 17:48
17:44 — Civil-1, Depot Block D
Piling complete — 48/48 piles. Pile cap casting commences tomorrow. On schedule.
RE: S. Mehta · 9 photos · GPS: 23.0741, 72.5038
17:31 — Civil-3, Chainage 14+200
TBM face settlement recorded 42mm. Work suspended. Geotechnical team en route.
HSE Officer: K. Rao · L3 escalation ESC-088 active
17:20 — Civil-2, Pier P-88
Formwork alignment deviation — 18mm out of tolerance. NCR NCR-CV2-041 raised.
QA Inspector: A. Verma · Corrective work ongoing
17:08 — Systems, Traction Substation 3
33kV cable termination complete. Pre-commissioning testing scheduled 06:00 tomorrow.
RE: P. Nair · 6 photos uploaded
16:52 — Rolling Stock, Depot Bay 4
Train set RS-07 static testing completed. Dynamic testing scheduled Week 14.
RE: V. Kulkarni · Test report submitted to PMO
16:38 — Civil-2, Chainage 8+400
Utility conflict — 200mm BWSSB water main not on drawings. 3-day hold. Design team informed.
Site Engr: R. Patel · Utility drawing request raised
Today's DSR summary6 packages
DSRs submitted (by 18:00)52 / 62
DSRs overdue10
HSE incidents today1 near-miss
NCRs raised today2
Milestones achieved3
Work stoppages active2
Photos uploaded today287
Drone surveys completed2
DSR submission rate — 30 days
Funder Reporting Engine
World Bank · ADB · JICA · AFD · AIIB — Auto-generated PPR · IFR · E&S Reports
ACTION REQUIRED:  E&S Quarterly Report overdue 18 days. GRM Quarterly Report not started. World Bank supervision mission in 14 days.
Funder reporting calendar — Q1 & Q2 2025
ReportStandardFrequencyNext DuePMO StatusFunderAlert
Project Progress Report (PPR)WB / ADBMonthly31 Mar 2025DraftingWorld Bank—
Interim Financial Report (IFR)World BankQuarterly15 Apr 2025On trackWorld Bank—
Environmental & Social ReportWB ESFQuarterly01 Apr 2025OverdueWorld Bank18 days late
Grievance Redress (GRM) ReportWB ESFQuarterly01 Apr 2025Not startedWorld BankUrgent
JICA Progress ReportJICA ODAMonthly05 Apr 2025On trackJICA—
Procurement Monitoring ReportWB GuidelinesQuarterly30 Apr 2025On trackWorld Bank—
Steering Committee DeckClient/FunderMonthly28 Mar 2025Final reviewSC + Funders3 days
Annual Progress Review (APR)All fundersAnnual30 Jun 2025PlanningAll—
Disbursement by funder — % utilised
World Bank disbursement conditions
Document Hub
Version-controlled repository · Drawing register · Correspondence log · MoM archive
Document categories
Contract documents418
Drawing register1,247
Correspondence log3,841
Meeting minutes (MoM)284
Progress reports96
Funder submissions47
Recent uploads
Today 16:30 — PMO Head
Steering Committee Deck v2.3 — March 2025
Today 14:15 — RE Civil-3
NCR-CV3-088 — Tunnel face settlement report
Yesterday — Siemens Mobility
IPC-SYS-07 with supporting measurement sheets
Yesterday — PMC Director
ESC-091 formal notice to CRRC Qingdao
Pending action — document review
Drawings awaiting approval34
Submittals under review12
Overdue MoM action items8
RFIs awaiting response19
Correspondence unanswered >7d5
Platform Settings
Cloud configuration · User management · Alert thresholds · Integration · Branding
Cloud hosting configuration
Hosting providerMicrosoft Azure (South India)
Uptime SLA99.9%
Data encryptionAES-256 at rest + in transit
Backup frequencyDaily (30-day retention)
Disaster recoveryRPO 4h · RTO 8h
API accessREST · OAuth 2.0
User roles & access
RoleUsersAccess Level
Platform Admin2Full admin
PMO Head1All modules
PMO Officers3Operational
PMC Director1Programme view
Funder (WB/JICA)4Read-only
Client PIU3Read-only
Site Engineers62Field input
Integrations
📅
Primavera P6
Schedule import / IMS sync
● Connected
📊
MS Project
Contractor schedule import
● Connected
📱
PlanRadar Mobile
Field DSR, photos, QC
● Connected
📈
Power BI
Executive dashboards
● Connected
📁
SharePoint
Document management
● Connected
✉️
MS Teams / Email
Alert delivery channel
● Connected
🗺️
GIS / Mapping
Site location tracking
◐ Configuring
🚁
Drone Integration
Monthly survey upload
◐ Configuring